Tag: Electricity

  • Ghana, Côte d’Ivoire to begin joint 330KV power line project

    Ghana and Côte d’Ivoire are set to commence the construction of a 330-kilovolt (kV) double-circuit transmission line as part of the West Africa Power Pool (WAPP) initiative.

    The 243-kilometre cross-border project is designed to boost electricity exchange between the two countries and enhance grid stability across the wider West African region.

    Feasibility studies have confirmed the project’s technical and financial viability within Ghana. The total estimated cost of the project is €154.4 million, covering environmental and social impact mitigation, construction supervision, and project management.

    Speaking at a ministerial committee meeting on Wednesday June 25, 2025, Chief Executive Officer of the Ghana Grid Company Limited (GRIDCo), Engineer Mark Baah, stressed the project’s role in deepening regional energy integration.

    “The project involves the construction of a 330kV double-circuit transmission line, stretching approximately 243 kilometres—about 122 kilometres on each side of the border,” he explained.

    “It will connect the existing Biahoué (Bijave) substation in Côte d’Ivoire to the upcoming Dunkwa 2 substation in Ghana. While there is currently a Dunkwa 1 substation, it operates at 161kV. This new facility in Dunkwa will operate at 330kV.”

    “Beyond enhancing bilateral energy trade, this project is expected to contribute to grid reliability across West Africa. It has been deemed both technically sound and environmentally manageable.”

    The initiative is a key step in the broader effort to integrate energy systems across the ECOWAS sub-region under the WAPP framework.

     

     

     

     

     

     

     

     

     

     

     

     

  • Ameri Relocation to Kumasi: gas pipelines & installation of plant almost ready

    Ameri power plant

     

     

    Adnan Adams Mohammed

     

    Information gathered indicates that, works on the Ameri power plant relocation to Ashanti region is almost completed with the gas pipelines ready.

     

    The installation of six units of the plant is also near completion.

     

    Although, the technical aspect of the project is almost done, the administrative aspects are yet to be concluded. The agreement to govern the interconnection and use of the pipeline is yet to be finalized.

     

     

    “Volta River Authority (VRA) and Genser Energy Ghana (GEGL) is negotiating an interconnection agreement to govern”, sources close to the project told this news medium.

     

    “Also, GNPC and VRA are yet to finalise the amendment to the GSA which allows for gas delivery to Kumasi.”

     

    “With the information I have, the Genser constructed pipeline is ready and even packed with gas. However that of the power plant is still pending. 6 units of Ameri have been transported.

     

    “Installation of the units started in August of last year”, the source further noted.

     

    The gas pipelines laid from Dawusaso to Kumasi is 105km.

     

    This project was initially met with hostility from some stakeholders and players in the energy sector. The Minority in Parliament raised concerns about the estimated cost of the project.

     

    According to the Minority, they noticed the anomaly when the Committee on Mines and Energy met with a number of Agencies in the Mines and Energy sector, as part of Parliament’s supervisory role.

     

    A Member on the Committee of Mines and Energy, Edward Bawa disclosed in a statement that when the Committee pushed further for details on the total cost for the relocation of the Plant, “answers were not forthcoming.”

     

    “One of the questions I put to the Volta River Authority was how much the relocation of the Ameri Plant from Tarkoradi to Kumasi was going to cost the Tax payer and which company was awarded the contract to execute this. You will recall that Government took the decision to relocate the Ameri Plant to Kumasi as part of efforts to stabilize the power in Kumasi and its environs,”.

     

    “To my outmost shock, the committee was told it was going to cost 35 million United States dollars. This is about 270 million Ghana Cedis,” Mr. Bawa disclosed.

     

    He continued: “The company contracted to carry out the relocation of the plant is MYTILINEOUS INTERNATIONAL TRADING COMPANY, the same company that was involved in the notations and amendment of the Ameri contract that almost swindled Ghanaians but for the vigilance of the Minority. You will also recall that this was what cost Minister Boakye Agarko his Job as Energy Minister.”

     

    “As a Minority we demand the breakdown of this cost particularly at a time when the country is having difficulties paying salaries and servicing our debt.

     

    “The Energy sector is under serious challenges and therefore such opaque transactions must be halted in the supreme interest of every Ghanaian,” the MP for Bongo stated.

     

     

  • Businesses demand load shedding timetable

    Electricity supply lines

     

    Adnan Adams Mohammed 

     

    Business operators and residential consumers are demanding from the Electricity Company of Ghana (ECG) to publish a load-shedding timetable as the erratic power supply situation continues to worsen in recent times.

     

    This follows after many Ghanaians expressed dissatisfaction with the ECG and the Energy Ministry for such a situation, which is a disturbing development and affecting businesses

     

    Key players in the industry, including the IES, have raised concerns over the situation, attributing it to financial challenges. But, the energy ministry has pleaded with Ghanaians to be a little patient as it works to resolve the challenge.

     

    “What has happened over the past few days is that some obligation owed by GNPC to WAPCo was an issue”, Deputy Energy Minister, Andrew Egyapa Mercer, has noted. “WAPCo threatened GNPC and it has made some initial payments, but it wasn’t satisfactory. We requested the Ministry of Finance to top up. We had to go through some approval processes.”  

     

    “As of yesterday [last week Wednesday] evening, the Ministry of Finance had approved a sum of US$10 million to pay for a part of that debt. So that was the hiccup that we encountered that led to the power outages we experienced in the past few days. But that has been resolved.”

     

    However, the Deputy Minority Leader, Emmanuel Armah-Kofi Buah has indicated that Ghana is currently grappling with “a severe case of load shedding, commonly known as ‘dumsor’”. 

     

    The situation, the former energy minister noted, “is evidently clear, with 500 MW of load being shed as of tonight, January 9, 2024”.

     

    The Ellembelle MP observed that “Numerous areas have been plunged into darkness due to the unavailability of gas to fuel thermal plants within the Tema enclave, which can be attributed to financial constraints”.

     

    Specifically, Mr Buah mentioned that the Ghana National Petroleum Corporation (GNPC) “is currently unable to fulfil its payment obligations to the West African Gas Pipeline, which is responsible for transporting gas from Takoradi to Tema for power generation”.

     

    “You can also track the ultimate problem to the weakest link in the value chain –ECG’s inability to pay off-takers”, he explained.

     

    “Compounding” the situation, Mr Buah added, “is the absence of a load-shedding timetable, which hampers households and businesses from planning accordingly”.

     

    To him, the “lack of transparency and communication regarding the power outage schedule only adds to the frustration and inconvenience experienced by the affected population”.

     

    “It is worth highlighting that even during the worst periods of dumsor in the past, the power outage never reached the 500-megawatts threshold currently being shed. Yet, the media associated with the NPP interestingly see this as no ‘dumsor’.”

     

    “Their loud silence on the current situation is deafening”, the lawmaker criticised.

     

    The Ghana Grid Company must, as a matter of urgency, come out with a load-shedding timetable to allow households and businesses to plan better”, he demanded.

     

    Some Ghanaians have been complaining about the power situation on Facebook for the past three days.

  • Ghana tops electricity access in Sub-Saharan Africa – Africa Pulse Report

    Ghana tops electricity access in Sub-Saharan Africa – Africa Pulse Report

    Memuna Asuma

     

    World Bank’s April 2023 Africa Pulse Report has rated Ghana as the first Sub-Saharan Africa with the largest electricity access rate.

     

    The West African nation recorded about 81% access to electricity rate in 2021, beat African power houses including South Africa, Kenya and Nigeria.

     

    In 2015, the country’s access to electricity in Africa stood at about 75%. That still placed it number one on the continent. However, between 2015 and 2021, the country added a little over 5.0% power to the electricity access rate. The World Bank’s Africa Pulse Report pointed out that the COVID-19 pandemic has had a sharp, adverse effect on access to electricity, adding, the pandemic eroded gains made in the preceding five years.

     

    “The pandemic eroded gains made in the preceding five years—the number of people without access to electricity increased by 4% in 2021, compared to 2019. This was the result of compounding challenges, including (1) limited fiscal and financial capacity to develop new grid and off-gird connections by both governments and households, and (2) lockdowns resulting in supply chain disruptions and other logistical disruptions”.

     

    However, in Ghana, Kenya, Rwanda, Senegal, and Côte d’Ivoire, the numbers were stable or reduced.

     

    The pandemic, it mentioned, had the largest effect on the installation of new stand-alone off-grid systems, as the majority of new connections since 2020 have been grid connections. Sales of independent solar home systems, including solar panels and batteries with a capacity of at least 20 watts, declined by roughly 20% in Sub-Saharan Africa between 2019 and 2021.

     

    Meanwhile, Côte d’Ivoire and Kenya were ranked 2nd and 3rd respectively in Sub-Saharan Africa with the biggest electricity access rate.

     

    COUNTRIES ELECTRICITY ACCESS RATE POSITIONS

    Ghana 81.2% 1st

    Côte d’Ivoire 77.0% 2nd

    Kenya 76.0% 3rd

    Senegal 73.5% 4th

    Nigeria 69.1% 5th

    Rwanda 65.0% 6th

    The Gambia 61.0 7th

  • New utility tariffs to take effect Sept 1

    New utility tariffs to take effect Sept 1

    Adnan Adams Mohammed

    Effective September 1, 2022, Ghanaians would be paying the approved adjusted tariffs for all electricity and water usage.

    According sources at the Public Utilities Regulatory Commission (PURC),the nationwide consultations on proposals it received from the utility companies, Electricity Company of Ghana (ECG) and Ghana Water Company Limited (GWCL) and others, was wrapping up to announce new tariffs this week.

    The PURC stakeholders’ consultation team reveals that, aside from the public a across the 16 regions, the PURC also engaged identifiable groups and relevant sections of the public and had considered all sides of the arguments in arriving at appropriate tariffs.

    A Daily Graphic publication last week indicated that, the new tariffs will not be across the board, which means the rates will depend on the reasons and proofs adduced by the utilities and the verification the commission has done. Also, the tariffs to be announced would exclude taxes and levies already imposed by the state.

    It said micro, small and medium enterprises (MSMEs), such as food joints and salons, would be protected from paying “punitive” tariffs.

    The utility companies presented proposals to the PURC in May this year, based on the regulator’s guidelines.

    While the Ghana Water Company Limited (GWCL) proposed a 300 per cent increment over its existing tariffs, the Electricity Company of Ghana (ECG) proposed 148 per cent, the Volta River Authority (VRA) proposed 37 per cent, with the Ghana Grid Company Ltd (GRIDCo) proposing 48 per cent.

    Other proposals were 38 per cent from the only private power distributor, Enclave Power, and 113 per cent increase over the existing tariffs of the Northern Electricity Distribution Company (NEDCo).

    The tariff proposals were in line with policy directions to progressively eliminate what has been described as “punitive tariff bands” that discouraged consumption.

    This included industry being made to pay higher to cushion residential consumers, a situation which was adding to the cost of doing business and making operations in the industrial sector costly.

    The multi-year tariff adjustment, which will come with different rates of increment over a five-year period, is also expected to enable the PURC and the utilities to commit to the quarterly “automatic” adjustment system, support industrial development and improve utility efficiency.

    Another source familiar with the consultations and computations told the Daily Graphic that in arriving at the various tariffs, the regulator took into consideration external and internal economic conditions, as well as the need to keep the utilities in operation, enabling them to do routine maintenance, finance developments, among others.

    The PURC also subjected all the costs proposed by the utilities to strict assessment and validation, including visiting some of the investments on the ground.

    It accepted servicing costs on loans for approved investments, while the state-owned utilities were asked to suspend all discretionary investment this year.

    The regulator also requested for and critically assessed proposed investments by utilities, among other things.

    Customer expectation survey The PURC also conducted a survey in which 851 respondents across all 16 regions completed the questionnaire.

    The survey indicated that 44 per cent of respondentsthought the current electricity tariffs were not commensurate with quality of service received from the electricity utilities due to frequent voltage fluctuations, poor customer service delivery, among other reasons.

    On electricity tariffs, 42 per cent of the respondents rated prevailing tariffs as fair, while 55 per cent rated them as high.

    Again, half of the respondents indicated that current water tariffs were not justified, given the poor service delivery in the form of frequent water supply interruptions. Consequently, 41 per cent of respondents rated prevailing water tariffs as fair, while 57 per cent rated them as high.

    The PURC, the source said, would also set efficiency benchmarks by which the utilities would abide, so that their inefficiencies would not be passed on to consumers.

    “The PURC sets loss benchmarks which mostly cover technical losses to ensure that the inefficiencies are not passed on. For instance, if the benchmark is 4.2 per cent and you incur 10 per cent, the PURC will deduct the benchmark and the utility will pay for the rest,”it explained. Fact sheet

    a) The utility companies are proposing new tariff adjustments mainly due to their inability to finance capital investments, inadequacy of the last PURC-approved tariffs, the depreciation of their assets, exchange rate fluctuations,payment of government-guaranteed loans, among others.

  • PURC extends announcement date of new utility tariffs by two weeks

    PURC extends announcement date of new utility tariffs by two weeks

    The Public Utilities Regulatory Commission (PURC), has set a new date for the announcement of its decision on the 2022-2027 Multi-Year Major Tariff Review.

    Last week Friday, 1st July 2022 was the initial date set for the announcement of the Commission’s decision on the review of water and electricity tariffs for 2022-2027, but, for the major interest of Ghanaians, had to extend the date to 15th July 2022.

    The Commission explained that the postponement was to allow for broadening of tariff consultation to solicit more independent views; independent verification of submitted projects (completed or work in progress) and deeper consultation with key stakeholders such as the utilities.

    “The above has led to the need for more time for further review of the tariff proposals submitted by the utility service providers, and to incorporate the findings of the regulatory audit and views of all stakeholders across the country”, a statement issued by the Commission and signed by Dr Ishmael Ackah said

    “The Commission has engaged most of its stakeholders, including the Parliamentary Select Committees on Finance; Mines and Energy; Water, Works and Housing; Development Partners; Civil Societies; Organized Labour; Industry; Media; Religious Groups; Academia, and the general public,” the statement added.

    The Commission assured all stakeholders of its commitment to ensuring a transparent, fair, and all-inclusive process in determining the multi-year tariff.

  • Electricity access in Ghana grew by 27% in 10years– report

    Electricity access in Ghana grew by 27% in 10years– report

    Adnan Adams Mohammed

    A African Development Bank (AfDB) report has indicated that, access to electricity in Ghana rose from 56.5 percent in 2012 to 83.5percent in 2021, translating into a 27% in a period of about 10 years.

    The current access rate of Ghana is estimated to be about two times of African Development Fund (ADF) beneficiary countries average rate.

    According to an AfDB report on Ghana’s power development, it estimated that, in urban areas nearly 94% of the population has access to electricity, and in rural areas, the share is 70%. This is three times higher than ADF countries’ average.

    “The share of the population with access to clean cooking solutions also increased markedly, growing from 16.4% in 2012 to 24.9% in 2021. This progress consolidated Ghana’s position as one of 10 countries in Africa whose access to electricity rate is the highest”, data contained in the report released, last week, noted.

    Between 2012 and 2021, Ghana almost doubled its total installed electricity capacity, leaping from 2.9 GW to 5.1 GW and generating more than 15,000 GWh. This includes an increase of installed renewable capacity from 1.2 GW to 1.7 GW, with hydropower taking the lion’s share (99%).

    The share of renewables in the energy mix declined, however, producing a fall in production efficiency, with more kilograms of CO2 emitted per dollar of Gross Domestic Product (GDP) in 2021 than in 2012.

    The upsurge in capacity and skills, which resulted in part from a rise in independent power producers’ generation of electricity, the report stressed, has allowed Ghana to resolve the major energy crisis that hit the country from 2012 to 2016 as a result of erratic rainfall that crippled hydroelectricity production in the Lake Volta region.

    The report however said electricity distribution remains a challenge in the country.

    Starting in 2017, the increase of generation capacity supplied Ghana with more power than was in demand (demand peaked at about 2.5 GW between 2012 and 2020).

    This absorption gap reflects pervasive shortfalls in the grid, which is hampered by inefficiencies in the distribution network and by skills gaps, especially in the installation and maintenance of energy equipment. Redressing these shortfalls, the report said, is critical to reducing the import of skills, which increases the cost of doing business in Ghana.

    As electricity losses through transmission, distribution, and collection are concerned, Ghana’s performance increased from 21.5% in 2012 to 22.6% in 2021, which is worse than ADF countries as a whole.

    To address this, the report said, government undertook certain governance-related actions, notably restructuring the legacy debts of the state-owned Electricity Company of Ghana (among other things, clearing its arrears) and reforming electricity tariffs to stimulate competition and encourage the private sector to participate in distribution.

    The Bank also shaped a more efficient distribution system within the framework of its support for the energy sector.

    AfDB said it will continue to support Ghana’s objective of supplying its citizens with universal access to energy by better generating and distributing electricity, among other things by  increasing off-grid connections in the country’s northern regions.

    The Bank is also standing with Ghana as the country manages climate risks, channels resources for adaptation, and transitions to green energy.

    “To reach its goals in this area, Ghana needs more investments in renewable energy-not just from one funder, but from many”, it said.

    In January 2022, the African Development Fund granted $27.4 million for the Ghana Scaling-Up Renewable Energy Programme. This contribution leveraged another $28.5 million in co-financing from the Climate Investment Funds and parallel financing of USD 13.3 million from Switzerland’s Secretariat for Economic Affairs.

    The programme will generate an estimated 111 MWh of renewable energy each year, thus contributing 13.5% of renewable energy to Ghana’s energy mix (excluding hydropower) and mitigating greenhouse emissions of 0.7 million tons of CO2-equivalent.

    The Bank’s ongoing Affirmative Finance Action for Women in Africa programme-to which the Green Climate Fund contributed $20 million-is another investment in clean energy.

    The programme is expected to reduce emissions by replacing diesel, fuelwood, and charcoal with renewable fuels, used sustainably. This operation and others like it will help supply the efficient, affordable, and sustainable energy that Ghana needs.

  • PURC shot-down the rate of increment proposed by ECG and GWCL

    PURC shot-down the rate of increment proposed by ECG and GWCL

    Adnan Adams Mohammed

    The Public Utilities Regulatory Commission (PURC), has indicated that utility service providers won’t get anything close to their huge tariff demands.

    This latest pronouncement is a reveler to many as the Commission is yet to complete its ongoing nationwide public hearing on the proposed tariff reviews.

    The Electricity Company of Ghana (ECG) has proposed an increment in tariffs by 148% while the Ghana Water Company Limited is asking for its tariffs to go up by 343%. This ignited a heated debate with majority of consumers opposing the proposed increment.

    “Though PURC is still considering a number of things, the utility firms will not get the huge margins they had proposed”, the Technical Committee Chairman of PURC, Ishmael Edjekumhene, has said when speaking at the Takoradi Public Hearing on the proposed tariff review for 2022-2027.

    “We are now beginning the detailed analysis of the proposals to see how prudent their (utilities) cost are to see the extent to which they’ve complied with the guidelines that we provided to them and then ultimately, once we’ve looked at all the numbers provided, we will take a decision. That decision can either go up, stay the same or come down because in 2018 the commission looked at all the numbers and was able to tell Ghanaians or tell the utilities that even though you are asking for an increment we think that the tariff should come down.”

    “So once we are satisfied with the analysis, what Ghanaians should expect is an announcement. If you go and compare the history of tariffs setting in Ghana and you compare the proposals as submitted by the utilities to what is ultimately approved, you will see that there’s a vast difference. It is not going to be a straightforward matter in the sense that we are coming to look at the numbers and what I’m certain of is that there is nowhere some of the things they are talking about are going to end up being the cost that consumers are going to pay”, he said.

    The Executive Secretary of the PURC, Dr. Ishmael Ackah also speaking at the Takoradi organized public hearing on the tariff proposals said the utility companies could have done themselves good if their service provision had been better all this while and could have helped them from the resistance by consumers to pay more.

    “47% of about 851 respondents in a survey we conducted indicated that they are willing to expect some adjustments on the condition that services will improve. So this year, in September, PURC is launching a customer service clinic so that utilities will tell customers that you can apply for a meter even if you don’t know any big man and that it will take you three days for you to get the meter even if you don’t know any honourable member. If we are able to do these things, I think it will reduce the number of PowerPoint slides you present at these forums just to make a case for the increment to consumers”, he said.

    The Public Utilities Regulatory Commission’s Takoradi Public Hearing on the proposed Tariff Review for 2022-2027 is the third after Accra and Ho in series of nationwide public hearings to enable utilities explain to consumers the rationale for their huge tariffs increment proposals.

    Meanwhile, majority of consumers who spoke at the Takoradi hearing shot down the tariff increment proposal.

  • Ghana signs $69.88m renewable energy deal to enhance electricity access

    Ghana signs $69.88m renewable energy deal to enhance electricity access

    Ghana has signed a $69.88 million renewable energy agreement to enhance electricity access in the next four years.

    Under the agreement, about 6,890 households, 6,001 Small and Medium-sized Enterprises (SMEs), and 6,890 public buildings will be connected to electricity.

    About 1,350 schools and 500 health centres would also benefit from the project, which would include the design, engineering, supply, construction, installation, testing, and commissioning of mini-grids and standalone systems.

    Seventy communities across nine Island districts through mini-grids, 505 communities in 11 districts through standalone solar photovoltaic (PV) systems in the country.

    The “Scaling-up renewable energy Programme (SREP),” is to close Ghana’s 12.8 per cent electricity reach deficit by increasing access to clean and reliable energy and support socio-economic development.

    It is to also help reduce public sector electricity debt as well as bills for SMEs and households while supporting the implementation of environmental, climate, and social management plans in the country.

    Mr. Ken Ofori-Atta, Minister of Finance signed the protocol agreement with Dr Akinwumi Akin Adesina, President of the African Development Bank (AfDB) Group.

    He also signed the financial agreement of the project with Mr. Dominique Paravicini, AfDB’s Governor for Switzerland.

    Speaking at the signing of the agreement, Mr. Ofori-Atta, said the project: “Dovetails fittingly into an urgent global agenda and demonstrates our country’s commitment to enhance the economic and social viability of low carbon investments.

    It is also in support of the country’s commitment to creating new energy-efficient markets and stave-off a future energy crisis by achieving energy sufficiency.

    The project also: “Fully align with the Government’s overarching ambition of increasing the contribution of Renewable Energy in the generation mix to 10 per cent by 2030 while achieving our emission reduction targets,” he added.

    Mr. Ofori-Atta indicated that the project would provide stable and cheaper electricity to hundreds of people across the country and usher in new economic opportunities, particularly for women in rural areas.

    On his part, Dr. Adesina noted that the project would support Ghana in meeting its renewable energy requirement on the Sustainable Development Goals (SDGs) and build a resilient economy.

    “This project will increase access to clean and reliable electricity services and support low carbon socio-economic development of Ghana. It will directly support Ghana’s efforts in building resilience to the socio-economic impact of the COVID-19 pandemic.”

    This would be done through the provision of electricity to healthcare centres, Island communities, enabling the refrigeration of vaccines and testing facilities for COVID-19.

    “The project will facilitate the self-sufficiency of Ministries, Departments, and Agencies (MDAs), through rooftop solar power generation and storage under the net metering component,” he added.

    Mr. Paravicini, said that the signing of the agreement showed Switzerland’s continuous support to bring sustainable and affordable electricity to households and businesses.

    SREP would be implemented between 2022 and 2025, under three components; the first would comprise of the development of 38 mini-grids and standalone solar PV systems for 2,000 SMEs, 1,350 schools, 500 health centres, and 400 communities.

    The second component, which is net metering, aims at up-scaling existing projects to about 12,000 units of roof-mounted net-metered solar PV systems to reduce public sector electricity debt and bills for SMEs and households.

    The final component would be the supervision of works including operating costs for the SREP Project Implementation Unit, Distribution Utility, and the implementation of environmental, climate, and social management plans.

    Source: GNA

  • Tariffs increment: will PURC consider economic hardship or face reality?

    Tariffs increment: will PURC consider economic hardship or face reality?

    Adnan Adams Mohammed

    The Public Utilities Regulatory Commission (PURC) has said this year’s approved tariffs for utility service providers will be announced on July 1, 2022.

    According to the PURC, the tariffs could be increased or decreased.  The Director of Research at PURC, Dr Eric Kofi Obutey, has said,  the Commission is engaging all the stakeholders to arrive at tariffs that will serve the need of Ghanaians as well as the service providers. The stakeholders as the Parliamentary Select Committee on Mines and Energy; Association of Ghana Industries (AGI), and Ghana Employers Association among others.

    The Electricity Company of Ghana (ECG) and Ghana Water Company Limited have proposed 148 per cent and 334 per cent hikes, respectively, in tariffs. This has triggered the anger of Ghanaians who complains that, the economy is already ‘burning the hell’ out of them, including policy analyst.

    Among the analysts who have reacted to the proposals is, Dr. Steve Manteaw. He has described the demand of increase in electricity and water tariffs as justifiable, saying, there is a strong basis for an upward adjustment, despite the inefficiencies of the utility firms. According to him, factors such as inflation and exchange rate losses justify the upward increment.

    “There is a strong basis for an upward adjustment; if you look at inflation rate, if you look at the cedi depreciation and all that. But what the companies haven’t told us is what component is made up of transmission losses and commercial losses. These are categorised us inefficiency cost”, The Executive Director of ISODEC said in an interview last week.

    “PURC has the mandate to ensure that inefficiency cost are not passed onto consumers. Of course to deal with inefficiencies, you need to make investments, but you don’t make investments from tariffs”, Dr. Manteaw expatiated.

    But, a Political Scientist and lecturer at the University of Ghana, Professor Ransford Gyampo, has questioned the proposal.

    Reacting to the proposed in a Facebook post, last week, he said: “You cannot propose an increment in utility bills across the board like that, at this time when the poor has already been hit hard.”

    He, therefore, wants “only article 71 officeholders, who have, but don’t pay, pay for such hikes,” to be made to pay the proposed increase by the utility service providers and “Leave the poor alone!”

    Apparently, a policy Think tank, Consumer Unity and Trust Society (CUTS) International, has backed the push for a review of utility tariffs by the Electricity Company of Ghana and the Ghana Water Company Limited.

    The think tank, however, maintains that there is the need to speedily address the inefficiencies within the system to make the companies sustainable.

    West Africa Regional Director for CUTS International, Appiah – Kusi Adomako, speaking in an interview explained that; “I support the principle that tariffs need to go up to make ECG able to fulfil its mandate. If ECG is deprived of increment, what it means is that ECG may not be able to invest. And we are told that most of the cables and other things are old and need replacement, or we might go back to the dumsor era. Water is also justifiable because the water company buys chemicals. These chemicals are imported into the country. Freight prices have also gone up, exchange rate has also gone up and even the cost of buying those items have also gone up between the last time tariffs were increased. So, we need to allow these firms to be able to get some increment so that the business will be sustainable. When it is sustainable, people will find them attractive to invest in,” he said.

    Furthering his argument, Dr Manteaw noted that, in normal business practices, shareholders are mandated to inject capital into the business with regard to equipment renewal and all the capital investments needed.

    “The shareholders in this case is the republic (government) and therefore we have to finance these major equipment renewal and maintenance activities from our taxes. They must be budgeted for through the budget and then in terms of the daily operations, you can actually finance through the taxes”, he added.

    He said the package given to Aqua Vitens Rand were far more and better conditioned than those given to Ghanaian entities, adding, “I do recall when we went through ECG privatization, we were prepared to do for PDS what we were not prepared to do for our Ghanaian managers”.

    For instance, he pointed out “when PDS took over, they asked that all the debts ECG had at the time were to be re-fenced. So it were not part of the account because those were legacy debts…they were not responsible. But we are not prepared to re-fenced for the old ECG”.

    “Again, a year before PDS took over, we had denied ECG tariff adjustment (upward adjustment). But when PDS took over, we gladly approved upward adjustment for PDS”, he added.

    Furthermore, Dr. Manteaw said “I tend to look at our utility companies sympathetically, a reason being that they really work under severe stress. And the conditions under which they work are not the type that any foreign multinational company will want to work under.”

    “I recall we brought in Aqua Vitens Rand, we improve water distribution in this country and by the time we abrogated – we actually refused to renew that contract – we had the phenomenon known as the Kufuor gallons. When the facility reverted to the Ghanaian manager, the gallons disappeared”, he stressed.

    Subsequently, the Ghana National Chamber of Commerce and Industry (GNCCI) says any adjustment must favour industries.

    According to the GNCCI, further increases, particularly in energy cost, will be detrimental to the private sector.

    The GNCCI notes that the PURC must consider cushioning the business community with a comparatively lower tariff that is reflected in the production capacity of manufacturing and key service sectors.

    Already, businesses are recovering from the impact of the pandemic in addition to rising cost of doing business.

    A statement issued by the GNCCI states that, “Energy is one of the critical cost components of business. While recognizing improvements in the energy situation over the last few years, energy cost to businesses remains too high (comprising up to 30% of cost of operation in some extreme cases). Businesses pay much higher energy in order to subsidize households. Whereas in many other countries, households pay higher energy cost to subsidize industry.”

    “As we move into the integrated African market zone, power tariff component of products will be a defining factor. Ethiopia and Kenya have better tariffs than Ghana; thus, making their products competitive.”

    In the proposal, ECG also wants 7.6% average adjustments between the periods of 2023 to 2026.

    The GWCL argues that while the average tariff per cubic metre in 2019 was 1.27 USD, it was reduced to USD 1.13 as a result of cedi depreciation.

    For the GWCL, the current domestic tariff of GHS3.29 per cubic metre to consumers within 0-5 cubic metres is less than what the poor in rural areas pay, which is about 10 cedis. The water company thus wants a 334% tariff hike.

    Considering the concerns and facing reality of the economic conditions at the a time inflation at reached all time highest in over 18 years to record 23.67 percent: Will the PURC consider the reality and dishonour or cut down the rate of increase being demanded by the utilities service providers, thus, ECG and GWCL; or it will consider the financial distress of the utility companies and give them what is due them to sustain their smooth operation?

    Ghanaians, ECG and GWCL are all now at the mercy of PURC decision to be announced on July 1.